Aryan Rathkanthiwar’s Eagle Project at Monte Vista High School

Categories: Eagle Project.

On February 24th 2024, for his eagle project, Aryan Rathkanthiwar constructed three shelving units for the Monte Vista Track and Field program. He had a huge appreciation to them as they have taught him discipline and dedication. The shelving units went inside their shed that they used to store athletic equipment. The coach was very grateful and the project was overall very successful.

 
 
 

He got a team of 9-11 scouts on both days and built the shelves and installed them into the shed using techniques that made building the shelving units more efficient.

 
 

       

The biggest challenges for him, were logistical issues as there were many issues that he didn’t account for, so he made solutions on the spot, and continued his project.

 

Overall, the project was over the span of 2 days, and was very successful, as the units are used for the school.